interEnergo Logo - Link zur Startseite

HPP Medna

Hydropower Plant Medna helped us expand our investments in Bosnia and Herzegovina by implementing Kaplan turbines. It is located on the Sana River and, due to ecological limitations, proved to be quite a challenge with one of the longest derivation tunnels in our portfolio. This project enabled the preservation of local ecology combined with electricity production.

General Information

  • Technology/Activity area: hydro power plant
  • Country: Bosnia & Herzegovina
  • River (basin): Sana
  • Total rated capacity: 4.9 MW
  • Status: in operation
  • Start-up: 2018

Key Figures

  • No. of turbines: 1
  • Type of turbine: Kaplan
  • Turbine manufacturer: Kössler
  • Type of installation: Run-of-river
  • Turbine capacity: 12.20
  • Net head: 47 m
  • Average annual electricity production/average output: 20,000 MWh
  • Annual CO2 savings: 9,800 t
  • Households powered with green energy annually: 6,700