HPP Novakovići

Hydropower Plant Novakovići is one of the best examples of Interenergo’s strategy of investments into hydro technology in the 2010’s. It is built on the Ugar River and uses vast internal know-how, gathered within the Group in the past 100 years, and has been producing green energy for more than 10 years already. 

General Information

  • Technology/Activity area: hydro power plant
  • Country: Bosnia & Herzegovina
  • River (basin): Ugar
  • Total rated capacity: 5.77 MW
  • Status: in operation
  • Start-up: 2012

Key Figures

  • No. of turbines: 2
  • Type of turbine: Francis
  • Turbine manufacturer: Gugler
  • Type of installation: Run-of-river
  • Turbine capacity: T1: 3,3; T2: 1,7
  • Net head: 144 m
  • Average annual electricity production/average output: 18,500 MWh
  • Annual CO2 savings: 9,070 t
  • Households powered with green energy annually: 6,200